The neocloud operator plans to fund its 2027 buildout largely through customer prepayments and contract-backed loans, but delays at a Microsoft-tied New Jersey site show how quickly that model can come under pressure.
Nebius told investors Thursday it plans to spend $40 billion to $45 billion in 2027, a figure well above what Wall Street had modeled. The announcement, delivered on the company's third-quarter earnings call, is bold by any standard in the neocloud sector. It is also built on a financing structure that is already cracking at the edges.
The company intends to fund this buildout largely through customer prepayments and loans backed by customer contracts. In effect, Nebius is borrowing against the future value of data centers it hasn't finished building. That approach works well when projects land on schedule. It becomes a liability fast when they don't.
CEO Arkady Volozh acknowledged as much on the call. "Building at this scale is hard, and delays are part of our industry right now," he said. "We are not immune." That admission lands at an awkward moment. Bloomberg reported last week that Microsoft is cooling on neocloud partners whose projects fall behind, scrutinizing deals with Nebius, IREN, and Nscale alike.
Microsoft is one of Nebius's largest customers, with a contract worth up to $19.4 billion tied partly to a data center in Vineland, New Jersey. That site is now months behind schedule. Only slightly more than half of the contracted Microsoft capacity is now expected to be delivered by year-end, with the remainder pushed to the second quarter of 2027, well past the original 2025 and 2026 delivery windows.
The cause, according to Nebius chief product and infrastructure officer Andrey Korolenko, traces to DataOne, the third-party operator running the Vineland site. DataOne wound down temporary power generation faster than planned as the facility transitions to Bloom Energy fuel cells. That transition wasn't entirely voluntary. Investigative outlet Floodlight found in August that DataOne was running at least 45 natural gas generators without the required permits. New Jersey regulators responded with a $1.1 million fine, citing a federal violation. The site also faces a separate lawsuit from nearby residents over constant humming noise.
Nebius's contract summary with Microsoft, filed with the SEC, gives Microsoft the right to terminate affected service after a grace period if deadlines are missed and no alternative capacity is offered. Financial penalties for late delivery are also built into the agreement. Nebius said Microsoft "has been part of the planning process" but declined to confirm whether Microsoft has formally signed off on the revised timeline. Microsoft has not publicly canceled anything, but its posture elsewhere suggests patience is limited. In its own quarterly report, Microsoft flagged lower-than-expected capex tied directly to third-party delays. Bloomberg also reported Microsoft won't exercise an option to more than double its Nscale agreement for a Texas site, and recently exited an anchor customer role at Nscale's planned Essex facility after power delays there. Microsoft reportedly sent staff to inspect the New Jersey site directly, a sign of heightened oversight rather than routine check-ins.

Nebius maintains the problem is contained. Chief revenue officer Marc Boroditsky said sites the company builds and controls itself are coming online on time or early, and those will supply the bulk of new capacity starting in 2027. He noted that new deals signed in the third quarter carried prepayments exceeding the cost of the capacity behind them. CFO Maria Del Dado Alonso Sanchez named Microsoft and Meta specifically as contracts eligible for this financing approach, with total prepayments and asset-backed financing from investment-grade agreements expected to cover up to 85% of the 2027 capex plan. Boroditsky added that Nebius could "tap prepayments to shore up any additional cash requirements" if needed.
The numbers behind the quarter were strong on the surface. Nebius reported third-quarter revenue of $981 million, up 571% year over year, though roughly a third of that figure reflects a one-time payment tied to a new partnership structure. The company ended the quarter with $7.4 billion in cash. Looking ahead, Nebius forecast 2027 revenue of $12 billion to $13 billion and said it expects to reach pre-tax breakeven by the fourth quarter of that year.
Not every figure moved in the right direction. Nebius cut its 2026 revenue forecast by $200 million, to $3 billion, directly citing delays at third-party sites like Vineland. Investors reacted accordingly. Shares closed the day down 17%.
Nebius is making a large bet that prepayments and contract-backed debt can carry it through a $40 billion to $45 billion spending year without the balance sheet strain that typically accompanies infrastructure buildouts of this size. The logic holds as long as customers keep paying ahead of delivery and projects stay on schedule. Vineland shows what happens when they don't: slipped deadlines, regulatory fines, lawsuits, and a major customer visibly tightening its oversight of the entire neocloud category.
The company's defense, that self-built sites are performing while third-party sites lag, is plausible but unproven at scale. Microsoft's broader retreat from underperforming neocloud partners, including its decision to pull back from Nscale commitments in Texas and Essex, suggests big tech buyers are losing patience with execution risk across the sector, not just at Nebius. For a company whose financing model depends on customer confidence staying intact, that's the risk worth watching most closely heading into 2027.
Tags
Original Sources
Nebius tests the neocloud playbook with $40 billion in planned spending | TechCrunch
↗ https://techcrunch.com/2026/11/12/nebius-tests-the-neocloud-playbook-with-40-billion-in-planned-spending
About the author
Marcus began tracking AI's market implications in 2016, noticing AI-related patent filings accelerating ahead of earnings upgrades before most of the sell-side had caught on. A former fixed-income quantitative analyst, he spent two decades building models that priced risk across emerging markets before pivoting to cover the economic impact of AI full-time. His writing translates opaque technical developments into clear risk/reward terms — and he's rarely diplomatic about the gap between AI valuations and underlying fundamentals. He believes most market participants still underestimate AI's long-run deflationary effect on knowledge work.
More from The Analyst →This Week's Edition
13 November 2026
14 articles
Related Articles
Related Articles
More Stories
© 2026 Cedar & Bloom. All rights reserved.